One Excelsior is the redevelopment of the previous Excelsior Hotel in Causeway Bay.  The new building will have 24 floors of premium Grade A standard office space with approx. 1,700 square metres of lettable space at each floor, enjoying uninterrupted view toward the Victoria Harbour.  There are also retail shops and restaurants situated in the podium floors, as well as about 140 nos. of car parking spaces in the 3-level basement.  The new development aspires to be an exemplar of latest smart building technologies, sustainable design features and low carbon construction.

環保特點

用地與室外環境

  • Wind performance in the urban area is maintained.

  • Daylight performance at the immediate neighboring residential developments is maintained.

  • Intruding noise from building equipment are acceptable for neighboring residential developments.

用材

  • > 50 % of composite wood products will be from sustainable source.

  • > 70% of building products are sourced manufactured regionally to reduce transport carbon footprint.

  • > 30% of construction wastes are recycled

能源使用

  • >22% of annual electricity consumption and > 19% peak demand is reduced through energy efficient features (e.g.  VSD chillers, cooling towers, and lighting, lift and escalator, etc.)

  • > 16% of total energy consumption in carpark are is supported by the proposed renewable energy system

  • Separate energy metering for separate monitoring of electricity use by the air side of the HVAC system; and metering for landlord’s electricity consumption in common space/public areas, etc.

用水

  • >51% of fresh water consumption is reduced through water efficient fixtures (e.g. faucets, shower heads, etc.)

  • >50% of fresh water consumption for irrigation is reduced though dripping/ compensated irrigation system

  • >10% of fresh water consumption for irrigation and AC make up is reduced through rainwater harvesting system

室內環境質素

  • Design measures for healthy and active living

  • Enhanced designs for barrier free

  • Target to achieve IAQ Excellent Class in Office and Common areas

  • Good acoustical environment are provided to reduce impact of noise

創新

  • > 100% of carparking spaces shall be equipped with EV charging-enabling

  • > 30% of carparking spaces shall be equipped with medium chargers with output power that is not less than 7kW


項目細節

竣工年份 2025
樓宇數目 1
樓層數目 31
類別 商業
總佔地面積 4,261 平方米

項目團隊

Developer Excelsior Hotel (BVI) Ltd.
Project Manager HKL (Project Management) Ltd.
Architect Ronald Lu & Partners (HK) Ltd.
Sustainable Design Consultant Allied Environmental Consultants Ltd.
Environmental Consultant Allied Environmental Consultants Ltd.
C&S Engineer Meinhardt (C&S) Ltd.
M&E Engineer WSP (Asia) Ltd.
Landscape Architect AECOM Asia Company Ltd.
Quantity Surveyor WTP (HK) Ltd.
Façade Consultant Meinhardt Façade Technology (HK) Ltd.
Acoustic Consultant Campbell Shillinglaw Lau Ltd.
Main Contractor Gammon Engineering & Construction Co. Ltd.