屯門業旺路公營房屋發展計劃第一期和第二期

  • 業旺路第一期和第二期效果圖 (鳥瞰圖)

  • 業旺路第一期和第二期的立面圖

  • 資訊管理及分析平台「智築目」的介面

  • 業旺路航拍照片

  • 業旺路航拍照片


新建建築 1.2版
暫定金級

整體得分

業旺路第一期及第二期公營房屋發展項目位於天后路,毗鄰屯門河,提供4 座住宅大樓和一個商場。

香港房屋委員會發展及建築處負責項目的規劃、設計、工程及合約管理。

這項目採用數碼技術和智慧設備實現可持續的公營房屋發展,包括在設計階段使用BIM,進行設計及施工協調,是房委會住宅項目中首批智慧工地之一。

業旺路項目亦是房委會首個進行「項目資訊管理及分析平台 - 智築目」的先導項目,這是一個針對房委會公共住房項目的綜合軟體解決方案,促進政策、規劃、施工監測和管理。

環保特點

用地與室外環境

  • 30% of site coverage of greenery

  • 58% of roof area was finished by roof material with SRI higher than 78 and vegetation

  • Environmental management to minimize air, noise and water pollution during construction

用材

  • Over 79% of the total CFA applying modular design

  • 62% of listed prefabricated building elements manufactured off-site within 800km of the site

  • 41% of regional manufactured material within 800km from the project site

能源使用

  • High energy efficient AC with better Coefficient of performance (CoP) and highly efficient lighting and lifts to reduce annual energy consumption

  • Separate metering to monitor landlord lighting and power, lift, P&D, AC and small power

用水

  • 29% of estimated annual water saving from the use of water efficient devices

  • 23% of reduction in annual sewage volume from the use of water efficient devices

室內環境質素

  • Building amenities to enhance the quality and functionality of the building

  • Enhanced designs for barrier free

  • Good class IAQ

創新

  • Twin tank for potable and flushing water supply
  • Provision of multi-sensory map with tactile guide path

  • Two Level Lighting system in public areas

  • Building Information Modelling (BIM) use in planning and design stage

  • Hard Paved Construction    

故事

Motivation to go “green”

It is noticed that building account for 90% electricity consumption or 60% greenhouse gas emissions in Hong Kong. As one of the largest housing providers in Hong Kong, the HA has been actively embracing innovation and technology to enhance the safety, efficiency, productivity, and sustainability of public housing development. The aim is to provide a better living environment to our citizen.

Way to enhances health and well-being

Innovative waste management measures to substitute the using of temporary refuse chute

As proposed by the contractor, material hoists are used instead of temporary refuse chute, to transport wastes / materials away from typical floor together with following achievements-

a. All wastes are sorted into waste for disposal or recyclable materials and stored at designated locations at typical floor. The quantity of non-inert waste disposed to landfill would be effectively reduced compared to other project with similar scale;

b. A Hilti On-Track System is installed to record the use of material hoist and the recycled materials digitally.  The quantity of recycled materials will be shown at the PIMAP Dashboard for real time monitoring.  To ensure only trained person can operate the material hoist, a face recognition system is adopted as well;

c. Different with traditional practice which normally the landing is accessed through the window opens at more than 1m above floor level, the landing level of material hoist at each floor is designed at the same level of the typical floor level which provides a safer construction environment for workers and allows using material hoist to deliver both the building materials and recycled materials more effectively and efficiency;

YWR Site Photo

Other

Traditional

Practice

d. Noise and dust pollution due to the operation of temporary refuse chute in traditional operation, especially from high level floor is avoided;

e. The quantity of Non-Inert Waste dumping to landfill site is largely reduced by 89%.

Smart solution - A Total Digital Solution for project management (PIMAP)

The HA has launched a GIS-BIM integrated Project Information Management and Analysis Platform (PIMAP) to effectively handle the extensive data generated by its numerous public housing projects. This system seamlessly integrates planning and design data, construction data, handover data, and open data from other sources.

During the construction stage of YWR project, the cloud-based open platform integrates data from smart site system, such as smart helmets, AI-enabled CCTV, RFID, site access control and recording system. It also incorporates BIM model, SUA scanning model of overall site progress, virtual reality 3D scanning model for sample flat. This platform offers a unified and convenient interface for all level project members to monitor the site activities and progress.

Furthermore, the system ensures a reliable record retrieving platform for the team to share, retrieve and compare records, including site photo easily in a complex and long duration construction project.

The implementation of PIMAP at Yip Wong Road Phase 1 and Phase 2 public housing project has been recognized with the Grand Award of OpenBIM/OpenGIS Awards 2023. In addition, the 4 dashboards derived from PIMAP have served as templates / samples for other HA projects to implement the digitalization system.

  


項目細節

竣工年份 2024
樓宇數目 4座
樓層數目 第一座: 41層 第二座: 40層 第三座: 38層 第四座: 41層
類別 住宅
總佔地面積 24,318.283 平方米

項目團隊

Developer 香港房屋委員會
Project Manager 香港房屋委員會
Architect 怡境師有限公司
Environmental Consultant 奧雅納工程顧問
C&S Engineer 邁進土木結構工程顧問有限公司
M&E Engineer 巴馬丹拿機電工程顧問有限公司
Landscape Architect 泛亞環境有限公司
Quantity Surveyor 利比有限公司
Facility Manager 香港房屋委員會屋邨管理處
Main Contractor 安保工程控股有限公司