A data services platform (DSP) will be set up at Cyberport 5 to provide convenient and flexible cloud data services, safe server rooms, and relating ancillary facilities for Cyberport’s start-ups to facilitate their development and testing of new products.  This platform can also offer suitable facilities and environment for promoting and enhancing cybersecurity training for the industry and provide crisis management simulation.

For the BEAM Plus Online Exhibition of the Host Building of Cyberport 5, please refer to this link: https://greenbuilding.hkgbc.org.hk/projects/view/1331

Green Features

Integrated Design and Construction Management

  • Engaging BEAM Professionals (NDC) from various disciplines for project management, design and construction to integrate green features.

  • Adequate mitigation measures during the construction phase to minimise air, noise, and indoor air pollution.

  • At least 60% of construction waste will be recycled.

  • Coordinated use of BIM for scheduling, cost and quantity, schedules preparation and tracking the project budget, and updating the BIM model to as-built condition. 

Sustainable Sites

  • Intruding noise at potential noise sensitive receivers will comply with the criteria recommended in “Technical Memorandum for the Assessment of Noise from Places Other than Domestic Premises, Public Places or Construction Sites”.

  • Obtrusive light from exterior lighting will comply with the specified performance for the environmental zone where the building is located.

Materials and Waste

  • At least 50% of all timber and composite timber products are from sustainable sources/recycled timber.

  • Use of refrigerants for air-conditioning and refrigeration equipment does not exceed the maximum threshold for ozone depletion and global warming. All major thermal insulation and fire-retardant materials for roof construction, walls, chilled water pipes, refrigerant pipes, ductwork will avoid using ozone depleting substances in their manufacture, composition or use.

  • Adoption of at least 4 best practices related to effective use of materials in Green Data Centre Practice Guide.

Energy Use

  • Adoption of passive design including optimised built form and orientation and external shading devices to reduce the space cooling energy consumption and maximise daylight.

  • Design to attain a PUE ratio of 1.31 to 1.37.

  • Energy metering to provide total facility power and energy usage and total IT equipment power and energy at the output of Power Distribution Units (PDUs) for determining instantaneous and average PUE.

  • Procuring UPS in accordance with certified energy efficient products scheme.

  • Adoption of best practices under Green Data Centre Practice Guide.

  • Holding Certificate of Compliance Registration (COCR) issued by EMSD to demonstrate compliance with BEC.

Water Use

  • Using of water efficient devices to achieve annual saving of at least 40% and reduce annual sewage volumes by at least 20%.

  • Installing water leakage detection system for the prevention of unnecessary water consumption.

  • Providing twin tank for potable water supply system and flushing water supply system.

  • Reducing fresh water consumption by installing water treatment system which can achieve 8 cycles of concentration with acceptable water quality.

Health and Wellbeing

  • Conducting thermal comfort measurement to demonstrate that the air temperature can be sustained at the design value within ±2.0°C when air side system in data halls is operating at steady state, and the air temperature can be sustained at the design value within ±1.5°C when air side system in normally occupied areas is operating at steady state under normal occupied periods.

  • Data halls (with lighting fixtures permanently installed), normally occupied spaces and unoccupied spaces will be designed to achieve the prescribed lighting performance.

  • Complying with the recommendations in Code of Practice for Prevention of Legionnaires’ Disease 2021 Edition in respect of water supply systems, HVAC systems and other water features. 

Innovations and Additions

  • Adopting Artificial Intelligence (AI) in Chiller Optimisation, a machine-learning technology in chiller plant system optimisation to achieve optimised model hence energy saving through operation scheduling, enhanced equipment energy efficiency, and ceasing the gaps between design and actual system operations.


Project Details

Completion Year Q4 of 2025
Number of Blocks 1
Number of Storeys One Storey of Data Services Platform
Type Others

Project Team

Project Developer / Owner Hong Kong Cyberport Management Company Limited
Project Manager Hong Kong Cyberport Management Company Limited
Architect Rocco Design Architects Limited
Landscape Architect AECOM Asia Company Limited
M&E Engineer WSP (Asia) Limited
C&S Engineer WSP (Asia) Limited
Facade Consultant AECOM Asia Company Limited
Main Contractor Gammon Construction Limited
Quantity Surveyor Rider Levett Bucknall Limited
Sustainable Design Consultant Ramboll Hong Kong Limited
Environmental Consultant Ramboll Hong Kong Limited
Acoustic Consultant Shen Milsom and Wilke, LLC
BEAM Plus NDC Consultant Aurecon Hong Kong Limited
Back

  • 1/F, Jockey Club Environmental Building, 77 Tat Chee Avenue, Kowloon Tong, Hong Kong.
  • +852 3994 8888
  • [email protected]

  • © 2024 Hong Kong Green Building Council Limited. All rights reserved.
  • Disclaimer

Stay connected:




© 2024 Hong Kong Green Building Council Limited. All rights reserved.
Disclaimer